|
- Preliminary License (LP) issued in May 2016.
- Installation and Operation License’s (LI and LO) issued in december 2018.
- Issuance of TLD (Termo de Liberação Definitiva) on December 20, 2019 for Mariana reinforcement.
- Energization scheduled for May 25, 2020.
- Issuance of TLD (Termo de Liberação Definitivo) on June 8, 2020, with date to entry into retroactive commercial operation on June 4, 2020.
- Concession in operation.
|
|
- All environmental licenses have been obtained: Installation and Preliminary Licenses of LT 500kV, LT 230Kv, SE Palmas, SE Lajeado, and SE Miracema.
- Recognition of the right to SUDAM’s tax benefit in September 2018. The benefit will last for 10 years from the start of its operations.
- The section LT Miracema – Lajeado (circuit 2), with 500kV of voltage and 30 km of extension, was energized in September 2019.
- Issuance of TLD (Termo de Liberação Definitiva) on October 1, 2019 for the reinforcement, on December 27, 2019 for the 500kV installations, and on February 18, 2020 for the 230kV and 138kV installations, where for the latter, a TLR (Termo de LIberação de Receita) was issued for the period between December 27, 2019 and February 7, 2020.
- Concession in operation.
|
|
- Preliminary License (LP) issued in June 2018.
- 2nd Inssuance of EDTE debentures in december 2018.
- Installation License (LI) issued in january 2019.
- Energizatoin of the TL 500kV Ibicoara – Poções III spread and the 500/230kV Poções III substation in December 22, 2019.
- Last energization of EDTE refers to the TL 230kV Poções III – Poções II spread on January 20, 2020.
- Issuance of TLP (Termo de Liberação Provisória) on January 20, 2020.
- Issuance of TLD (Termo de Liberação Definitiva) on February 7, 2020.
- Concession in operation.
|
|
- Basic project registered with ANEEL and already approved in ONS.
- Preliminary License (LP) issued in January 2019.
- Installation License (LI) issued in October 2019.
- 1st issuance of debentures of ESTE in December 2019.
- Issued the OSC (Ordem de Serviço de Campo) for the start of field work.
- Project concluded and awaiting ONS in order to energize.
|
|
- Basic project is approved by ANEEL/ONS for the substations and under review for transmission lines.
- The design implementation / topography activities were completed.
- Preliminary License (LP) issued in September 2018.
- Financing agreement signed with BNB in September 2018.
- Recognition of the right to SUDENE’s tax benefit in September 2018. The benefit will last for 10 years from the start of its operations.
- 1st Issuance of Janaúba debentures in January 2019.
- Installation License (LI) issued in July 2019.
- 2nd issuance of Janaúba debentures in December 2019.
- Concession in operation.
|
|
- Basic project approved by ANEEL.
- Preliminary License (LP) issued in October 2018.
- Recognition of the right to SUDENE’s tax benefit in December 2018. The benefit will last for 10 years from the operating start of the project.
- Installation License (LI) issued in April 2019.
- Concession in operation.
|
|
- Basic project registered with ANEEL.
- Preliminary License (LP) issued in October 2018.
- Recognition of the right to SUDENE’s tax benefit in December 2018. The benefit will last for 10 years from the operating start of the project.
- Instalation License (LI) issued in May 2019.
- Issuance of TLD (Termo de Liberação Definitiva) on July 27, 2022.
- Concession in operation.
|
|
- Basic project filed in ANEEL.
- EIA/RIMA registered with IAP.
- Preliminary License (LP) for the 230kv installations issued in September 2018.
- Change in corporate name of Elétricas Reunidas do Brasil S.A. (ERB1) for Electric Interconnection Ivaí S.A.
- Instalation License (LI) issued for Sarandi Substation of 525/230 kV in April 2019, Paranavaí Norte Substation of 230/138 kV in May 2019, LT 230 kV Sarandi – Paranavaí Norte in June, 2019, and for the Substations Londrina of 525 kV, Foz do Iguaçu of 525 kV and Guaíra of 525 kV/230 kV, and the LT 525 kV Sarandi – Londrina in August 2019.
- 1st issuance of debentures of Ivaí in January 2020.
- Construction Progress: 98% accomplished.
|
|
- Establishment of the company Sant’Ana Transmissora de Energia S.A. on January, 2019.
- Execution of the concession agreement on March 22, 2019.
- Previous and Installation Licenses (LPI) issued for the SSs Livramento 3 and Maçambará 3, both with 230kV, in October 2019.
- Previous Licenses (LP) issued for all lines of transmission and for the 3 existing substations (SS Alegrete 2, SS Cerro Chato and SS Santa Maria 3) in December 2019.
- Installation Licenses (LI) issued for the transmission lines LT Livramento 3 – Alegrete 2 (C1), LT Livramento 3 – Maçambará 3 (C1), LT Livramento 3 – Cerro Chato (C1), and sectionings LT Maçambará – Santo Ângelo (C1/C2), all of 230kV voltage, as well as for the extensions to substations SE 230kV Alegrete 2 and SE 230kV Cerro Chato, in April 9, 2020.
- Last Installation License referring to the LT 230kV CS Livramento 3 – Santa Maria 3, which represents approximately one third of the total extension of the transmission lines of this concession was issued on November 11, 2020.
- Construction progress: 88% accomplished.
|
|
- Incorporation of the company Ananaí Transmissora de Energia Elétrica S.A. in December 2021 for
build and operate Lot 1 of Auction 002/2021.
• Concession contract formally signed on March 31, 2022
|
|
- Incorporation of the company Pitiguari Transmissora de Energia Elétrica S.A. on June 2022 to build and
operate Lot 10 of Auction 01/2022.
|
|
• Incorporation of the company Tangará Transmissora de Energia Elétrica S.A. on December 2022 to build and operate Lot 03 of Auction 02/2022.
|
|
• Incorporation of the company Tangará Transmissora de Energia Elétrica S.A. on December 2022 to build and operate Lot 05 of Auction 02/2022.
|
|