|
- Preliminary License (LP) issued in May 2016.
- Installation and Operation License’s (LI and LO) issued in december 2018.
- Issuance of TLD (Termo de Liberação Definitiva) on December 20, 2019 for Mariana reinforcement.
- Energization scheduled for May 25, 2020.
- Issuance of TLD (Termo de Liberação Definitivo) on June 8, 2020, with date to entry into retroactive commercial operation on June 4, 2020.
- Concession in operation.
|
|
- All environmental licenses have been obtained: Installation and Preliminary Licenses of LT 500kV, LT 230Kv, SE Palmas, SE Lajeado, and SE Miracema.
- Recognition of the right to SUDAM’s tax benefit in September 2018. The benefit will last for 10 years from the start of its operations.
- The section LT Miracema – Lajeado (circuit 2), with 500kV of voltage and 30 km of extension, was energized in September 2019.
- Issuance of TLD (Termo de Liberação Definitiva) on October 1, 2019 for the reinforcement, on December 27, 2019 for the 500kV installations, and on February 18, 2020 for the 230kV and 138kV installations, where for the latter, a TLR (Termo de LIberação de Receita) was issued for the period between December 27, 2019 and February 7, 2020.
- Concession in operation.
|
|
- Preliminary License (LP) issued in June 2018.
- 2nd Inssuance of EDTE debentures in december 2018.
- Installation License (LI) issued in january 2019.
- Energizatoin of the TL 500kV Ibicoara – Poções III spread and the 500/230kV Poções III substation in December 22, 2019.
- Last energization of EDTE refers to the TL 230kV Poções III – Poções II spread on January 20, 2020.
- Issuance of TLP (Termo de Liberação Provisória) on January 20, 2020.
- Issuance of TLD (Termo de Liberação Definitiva) on February 7, 2020.
- Concession in operation.
|
|
- Basic project registered with ANEEL and already approved in ONS.
- Preliminary License (LP) issued in January 2019.
- Installation License (LI) issued in October 2019.
- 1st issuance of debentures of ESTE in December 2019.
- Issued the OSC (Ordem de Serviço de Campo) for the start of field work.
- Project concluded and awaiting ONS in order to energize.
|
|
- Basic project is approved by ANEEL/ONS for the substations and under review for transmission lines.
- The design implementation / topography activities were completed.
- Preliminary License (LP) issued in September 2018.
- Financing agreement signed with BNB in September 2018.
- Recognition of the right to SUDENE’s tax benefit in September 2018. The benefit will last for 10 years from the start of its operations.
- 1st Issuance of Janaúba debentures in January 2019.
- Installation License (LI) issued in July 2019.
- 2nd issuance of Janaúba debentures in December 2019.
- Concession in operation.
|
|
- Basic project approved by ANEEL.
- Preliminary License (LP) issued in October 2018.
- Recognition of the right to SUDENE’s tax benefit in December 2018. The benefit will last for 10 years from the operating start of the project.
- Installation License (LI) issued in April 2019.
- Concession in operation.
|
|
- Basic project registered with ANEEL.
- Preliminary License (LP) issued in October 2018.
- Recognition of the right to SUDENE’s tax benefit in December 2018. The benefit will last for 10 years from the operating start of the project.
- Instalation License (LI) issued in May 2019.
- Issuance of TLD (Termo de Liberação Definitiva) on July 27, 2022.
- Concession in operation.
|
|
- Basic project proposal filed with ANEEL.
- EIA/RIMA registered with IAP.
- Preliminary License (LP) for the 230 kV installations issued in September 2018.
- Change in corporate name of Elétricas Reunidas do Brasil S.A. (ERB1) for Interligação Elétrica Ivaí S.A.
- Installation Licence (LI) issued for SE Sarandi of 525/230 kV in April 2019, SE Paranavaí Norte – 230/138 kV in May 2019, LT 230 kV Sarandi – Paranavaí Norte in June 2019, and for the Substations Londrina of 525 kV, Foz do Iguaçu of 525 kV and Guaíra of 525 kV/230 kV and the LT 525 kV Sarandi – Londrina in August 2019.
- 1st issuance of debentures of Ivaí in January 2020.
- Provisional Release Terms issued (i) in November 2022, for the 525kV corridor for the LT Foz do Iguaçu – Guaíra transmission lines (double circuit), 525 kV General Modules of SE Foz do Iguaçu and SE Guaíra, Banks of 525 kV Reactors at SE Guaíra, and (ii) in May 2023, for the 525/230 kV Transformer Banks at SE Guaíra. TLDs issued for these segments in May 2023.
- Provisional Release Terms issued for the 525 kV corridor for the LT 525 kV Guaíra – Sarandi transmission lines (double circuit) in November 2022, with TLD issued in December 2022.
- Provisional Release Terms issued for the 525kV corridor of the SE Guaíra Reactor Banks in November 2022, with TLD issued in January 2023.
- Provisional Release Terms issued for the start of commercial operation of the Capacitor Bank 138kV-30 Mvar of SE Paranavaí Norte, the General Mode 230 kV of SE Paranavaí Norte with interconnections, Transformer Banks 230/138 kV of SE Paranavaí Norte, LT 230 kV Sarandi – Paranavaí Norte (double circuit) and 138 kV Paranavaí line inputs and LT 230 kV Sarandi-Paranavaí Norte (double circuit) in January 2023, TLD issued in April 2023.
- Provisional Release Terms and TLD issued for LT 525 kV Sarandi – Londrina C1 in November 2022. Provisional Release Terms issued for LT 525 kV Sarandi – Londrina C2 in November 2022. TLD issued for General Module 525 kV of SE Londrina in November 2022.
- Provisional Release Terms issued for the 525 kV General Model of SE Sarandi, the 525 kV Reactor Banks of 525/230 kV – 150 Mvar, and the 525/230 kV Reactor Banks of SE Sarandi in November 2022.
- Provisional Release Terms issued for the 525 kV General Model of SE Sarandi, the 525 kV Reactor Banks of 525/230 kV – 150 Mvar, and the 525/230 kV Reactor Banks of SE Sarandi in November 2022. TLDs issued for these sections in August 2023.
- Construction progress: 100.0% accomplished as of March 31, 2024.
- Complete commercial operational start-up as of March 3, 2024.
|
|
- Establishment of the company Sant’Ana Transmissora de Energia S.A. in January 2019.
- Execution of the concession agreement on March 22, 2019.
- Previous and Installation Licences (LPI) issued for the SEs Livramento 3 and Maçambará 3, both with 230kV, in October 2019.
- Previous Licenses (LP) issued for all transmission lines and for the 3 existing substations (SE Alegrete 2, SE Cerro Chato and SE Santa Maria 3) in December 2019.
- Installation Licence issued for the transmission lines LT Livramento 3 – Alegrete 2 (C1), LT Livramento 3 – Maçambará 3 (C1), LT Livramento 3 – Cerro Chato (C1), and LT Maçambará – Santo Ângelo (C1/C2), all with 230kV voltage, as well as for the expansion of existing substations of SE 230kV Alegrete 2 and SE 230kV Cerro Chato on April 9, 2020.
- Issuance of the last installation license in November 2020 referring to the LT 230kV CS Livramento 3 – Santa Maria 3 and for the expansion of existing associated substations.
- Release Terms issued on April 1st, 2022, retroactively dated for March 28, 2022, for transmission lines LT Livramento 3 – Alegrete 2 e LT Livramento 3 – Cerro Chato and part of substation SE 230 kV Livramento 3.
- Release Terms issued on December 7, 2022, retroactively dated for November 30, 2022, for transmission lines LT Livramento 3 – Maçambará 3, substation SE Santa Maria 3 and Subsection Maçambará – Santo Ângelo em Maçambará 3 C1.
- Energization of the stretch of LT Livramento 3 – Santa Maria 3 and SE Santa Maria 3 on May 2, 2023.
- Energization of the Livramento 3 SE Synchronous Compensator on May 18, 2023.Energization of the Maçambará – Santo Ângelo Sectioning in Maçambará 3 C2 on August 25, 2023.
- Construction progress: 100% accomplished as of December 31, 2023.
- Complete operational start-up in December 2023.
- Note: The project became fully operational and currently receives ~96% of its RAP due to technical
issues that are being reconciled with ANEEL and once resolved, Sant’Ana will receive 100% of its
RAP.
|
|
- Incorporation of the company Ananaí Transmissora de Energia Elétrica S.A. in December 2021 to build and operate Lot 1 of Auction 02/2021.
- Concession contract formally signed on March 31, 2022
- Preliminary License (LP) for the section of LT Bateias – Curitiba Leste issued in August 2023 and for the section of LT Ponta Grossa – Assis issued in September 2023.
- Preliminary License (LP) for the section of LT Bateias – Curitiba Leste issued in August 2023 and for the section of LT Ponta Grossa – Assis issued in September 2023.
- Construction progress: 31.9% accomplished as of June 30, 2024.
|
|
- Incorporation of the company Pitiguari Transmissora de Energia Elétrica S.A. on June 2022 to build and operate Lot 10 of Auction 01/2022.
- Concession contract formally signed on September 30, 2022.
- Preliminary License (LP) for the LT Abdon Batista – Videira and LT Abdon Batista – Barra Grande sections issued in August 202
- Construction progress: 53.6% accomplished as of June 30, 2024.
|
|
- Incorporation of the company Tangará Transmissora de Energia Elétrica S.A. on December 2022 to build and operate Lot 03 of Auction 02/2022.
- Concession contract expected to be signed on March 30, 2023.
- Construction progress: 28.9% accomplished as of June 30, 2024.
|
|
- Incorporation of the company Tangará Transmissora de Energia Elétrica S.A. on December 2022 to build and operate Lot 05 of Auction 02/2022.
- Concession contract expected to be signed on March 30, 2023.
- Garabi I and II units and Transmission Lines LT Santo Ângelo – Itá, LT Garabi 2 – Santo Ângelo, and LT Garabi 1- Fronteira are operational with active RAP (phase 1) as of March 31, 2023.
- Reinforcements (phase 2) – Construction progress: 45.0% accomplished as of June 30, 2024.
|
|
|
|